Rockland Highway Department Begins Largest Road Resurfacing Program

Rockland County Executive C. Scott Vanderhoef has announced that the Rockland County Highway Department initiated its largest paving and resurfacing program that includes over 428,064 square yards, approximately 20 miles, of pavement at a projected cost of $4.8 million. Much of the 2012 road program was delayed due to Hurricane Sandy and an exceptionally bad winter that took a toll on roads in the county.

โ€œThe countyโ€™s superintendent of Highways, Skip Vezzetti, and his dedicated staff, will be hard at work during the next few months utilizing various processes including hot-in-place recycling, milling, conventional paving, chipsealing and microsealing to improve our roads throughout the county,โ€ said Vanderhoef.

In order to perform on schedule, the milling and paving operations of roads will be done concurrently. The same applies to the hot-in-place operation that will be done concurrently with the microsealing and chip-sealing processes. Line striping of the roads will occur during the summer months of July and August.

OVERLAYS
Middletown Road (Route 59 to Smith)
Little Tor Road (W. Clarkstown to Milich Lane)
Eckerson Road (Route 45 to W. Clarkstown Road)
New City – Congers Road (Rte 304 to Brewery)
Townline Road (Ehrhardt to Sickletown)
Sanatorium Road (Rte 45 to Summit Park Road)
Sterling Mine Road (Arcadia to Rte 17)
Pomona Road (Rte 306 to Rte 45)
Airmont Road (Dunnigan to Montebello)
Strawtown (Demerest to Germonds)
West Clarkstown (New Clarkstown to Red Hill Rd)
New Hempstead Road (Rte 45 to Summit Park)

All roads will be milled 2 inches then resurfaced. Paving has begun on Middletown. All roads to be completed by end of May. Airmont Road between Dunnigan Drive and Montebello will be scheduled for night work with a date to be established in coordination with the NYS Thruway.

MICROSEAL
Old Nyack Turnpike (Pascack Road to end)
Hammond Road (Suffern Lane to Willow Grove)
Washington Street (Main Street to Dederer)
S. Monsey Road (Saddle River to Christmas Hill)
College Road (Rte 59 to Highview)
Cherry Lane (Christmas Hill to Rte 59)Airmont Road (NJ line to Route 59)
Washburns Lane (Central Hwy to Rte 9W)
Tomkins Ave (Rte 9W to Beach Rd)
Strawtown (Germonds to 235 Strawtown)
Central Highway (S. Mtn Rd to Town border)Sickletown Road (Townline to W. Nyack Rd)

All microseal roads will receive a hot- in-place treatment prior to microsealing. Hot-in-place treatment has begun on Strawtown and Sickletown roads. The hot-in-place treatment will continue until the end of May. All microseal roads will be completed by the second week of July.

CHIPSEAL
Strawtown Road (235 Strawtown to Westerly)
Gilbert Ave (Veterans Mem to Sickletown)
Old Mountain Road (South Blvd to Rte 9W)
Viola Road (Galbraith to Forshay)
Wilder Road (Lime Kiln to Rte 202)
Green Road (Sickletown to Western Hwy)
River Road
Greenbush Rd (Clausland Mtn to Rte 303)
Greenbush Rd (Bradley Pkwy to Rte 303)
Viola Road (Spook Rock to Galbraith)
Spook Rock Road (Grandview to Spook Rock)
Spook Rock Road (Highview to Grandview)
Spook Rock Road (Lime Kiln to Grandview)
Johnsontown Road
Reservoir Road (Rte 210 to W. Main Street)
West Main St (Wayne Ave to Rte 9W)

Chipsealing of roads will begin the last week of May. All roads will be completed by the middle of June.

You must be logged in to post a comment Login