STORY AND PHOTOS BY JANIE ROSMAN
Another page of bridge history took place last week when the I Lift NY fitted a 600-ton precast concrete pile cap on a set of piles.
It was the super craneโs first of many placements and future lifts.
โYou have the tub that sitting over four piles that are accepting the load, so precision is key,โ Prof. Ted Zoli, HNTB National Bridge Chief Engineer on the bridge project explained.
Strong winds and choppy waters were no match for the craneโs precision and zero margin for error.
โYouโre surveying it and want to hold it (tub) vertically so youโre not changing the position of the load,โ Zoli said. Cleared around the piles, the arm began lowering the tub carefully, slowly, within that clearance.
The piles were supported on four adjustable beams โthat will support the pile cap once the crane lets go,โ Zoli said. The cap will be lowered into position, and each beam will be wound down to the top of each pile to support the pile cap on them. โOnce contact is made, and the load is taken off the crane, the four beams are used to continuously lower the pile cap to its final precise place.
Tubs will then be filled with rebar and concrete.
Perched on a 384-foot barge, the lifter was anchored by spuds (like parking brakes) plunged 60 to 70 feet into mud (depending upon floor elevation). With neither a steering system nor self-propulsion, it was moved and positioned by tugboats, and maneuvered by anchors running out 600 feet from the sides, once the spuds were pulled up. Its power comes from three diesel-powered main generators and one auxiliary generator.
โWe brought in the I Lift NY super crane to reduce construction time and cost, and this first lift is another symbol that the New NY Bridge is officially on the way,โ Thruway Acting Executive Director Robert L. Megna.
Following a six-week journey from Oakland, CA, days before Christmas 2013 โ escorted by tugboats Lauren Foss and Iver Foss โ the super crane arrived at The Port of New York and New Jersey. It was sent to a private facility in Jersey City, where it was prepped and did test lifting before traveling to the project site.
Owned by bridge builder Tappan Zee Constructors, LLC (TZC), it sits high in the water, reducing the projectโs dredging needs by 50 percent.
Its lifting power (1700 metric tons or 1929 US tons) from three diesel-powered main generators and one auxiliary generator incorporated into the barge will hoist and place sections โ some weighing 900 to 1,000 tons โ of the new twin-span bridge and will assist when the current bridge is dismantled.
You must be logged in to post a comment Login