STORY AND PHOTO BY JANIE ROSMAN

After a ceremonious welcome last month that promptedย a visit from Governor Cuomo, theย I Lift NYย super crane might appear to be โhanging outโ in the Hudson River.
Its limbo maneuver under the bridge โ extra low tide that evening added an extra foot or two of clearance โ two days after its arrival was nothing compared to what the crane with super strength and no navigational power of its own can do.
After its six-plus-week trek from Oakland, CA, and recent docking at Jersey City, it arrived ready to set sections of pre-fabricated steel desk, 350 feet long each, from about 100 miles north at Port of Coeymans beforeย New Yearโs Eve.
Currently perched on a 384-foot barge, the lifter is anchored by spuds (like parking brakes) plunged 60 to 70 feet into mud (depending upon floor elevation). With neither a steering system nor self-propulsion, it will be moved and positioned by tugboats, and maneuvered by anchors running out 600 feet from the sides, once the spuds are pulled up.
โItโs in the process of being prepared for use,โ which will be near mid-December, according to Tappan Zee Constructors, LLC (TZC) construction manager and New City resident Ro DiNardo. โThat willย be the first time we use the Left Coast Lifter.โ
Dubbed theย I Lift NYย months earlier, the crane is owned by TZC and is officially named the Left Coast Lifter. Whatโs in a name, anyway?
Running on Windows 7, and with new computer software, hardware, and a flat panel touch screen, the crane is currently being readied to lift four oversized pile caps (too heavy for conventional cranes to set) in mid-December.
Prepping involves getting the frame together (versabar) that will make the placement. โIt will take a little time, anchor tests will be scheduled during the next two weeks,โ things unseen that are necessary to get the crane to work, DiNardo said.
The new bridge will be supported by 86 columns, most of them for the main span approaches in Westchester and Rockland. Construction crews are working on the main span, where oneย concrete batch plantย is now. The second plant, onsite, is not in use yet.
โWe started pouring concrete into the footings today near the Westchester side, focusing on Pier 39 columns,โ DiNardo said. By the end of next week, youโll see those columns in the air. On the Rockland side, crews are installing precast concrete tubs (pile caps) that are first filled with rebar, then with concrete, and then brought up to grade.
DiNardo smiled when asked about doing things today versus in days of yore.
โTechnology, the way they did things (with the) first bridge, and the way weโre doing things now, is enhanced,โ he said. โI have great appreciation for how they built the Tappan Zee Bridge, and am thankful we have this crane to build the new bridge with better quality and more efficiently.โ
When you see the crane moving, look for Ron Burgess, who operated cranes as a teenager on the New Rochelle waterfront, in the driverโs seat with partner and operator Doug Cormey, in addition to others.
The aforementioned anchors are controlled from the cab (where the driver sits).
โWhen they go to set the first beam (of the new bridge), the versabar (system) is capable of picking up 1700 metric tons, which is 1928 US tons,โ Burgess said.
Its lifting power โ from three diesel-powered main generators and one auxiliary generator that are incorporated into the barge โ will enable it to hoist pre-assembled connected steel girders onto the foundation piers.
Standing at RiverWalk Park in Tarrytown or in Nyackโs Memorial Park, itโs difficult to ascertain how large theย I Lift NYย crane is without a marker or reference.
Once on the river, though, youโve no doubt.
Pingback: Personal Musing: Yesterday on the Bridge | Kaleidoscope Eyes
Pingback: RPI Engineering Students Visit Praegerโs Successor | Kaleidoscope Eyes
Pingback: The terrifying rise of West African piracy